NFPA 25 is the standard most US fire codes reference for the inspection, testing, and maintenance (ITM) of water-based fire protection systems. In New Jersey, New York, and Connecticut, the state fire codes point building owners to NFPA 25, which makes the owner responsible for having the work done and keeping the records.

Who is responsible

NFPA 25 places responsibility for ITM on the property owner or a designated representative (often the property manager). The owner can hire a qualified contractor to do the work, but the obligation to keep the system in service and keep records stays with the owner.

Keep inspection, test, and maintenance records for the life of the system where the standard calls for it, and at least until the next equivalent test for routine items. Your AHJ or insurer may ask to see them.

Common frequencies at a glance

Frequencies below summarize recent editions of NFPA 25. Your jurisdiction may enforce an older or newer edition, and your insurer or the authority having jurisdiction (AHJ) can require more. Treat this as a checklist to discuss with your contractor, not as legal advice.

FrequencyTypical tasks (wet and dry sprinkler systems)
Daily / weeklyIn cold weather, dry-pipe and preaction valve enclosures are checked daily (weekly if equipped with a low-temperature alarm); diesel fire pump no-flow (churn) run weekly.
MonthlyControl valves that are only sealed (not locked or electrically supervised); gauges on dry, preaction, and deluge systems; electric fire pump no-flow run (some pumps must still run weekly).
QuarterlyWaterflow alarm devices and supervisory signal devices inspected; mechanical (water-motor gong) alarms tested; fire department connections inspected; locked or supervised control valves inspected; quick-opening devices and dry-pipe priming water level checked; main drain test where the system is supplied through a backflow preventer or pressure-reducing valve.
SemiannuallyVane-type and pressure-switch waterflow alarm devices tested; valve supervisory switches tested.
AnnuallySprinklers, pipe, fittings, hangers, and spare-sprinkler cabinet inspected from the floor; main drain test; control valves operated through full travel; dry-pipe valve partial-flow trip test; antifreeze solution tested; backflow preventer forward-flow test; fire pump flow (performance) test; hydraulic design nameplate checked.
Every 3 yearsDry-pipe valve full-flow trip test; dry-system air-leakage test.
Every 5 yearsInternal pipe assessment for obstructions; check valves internally inspected; alarm valve and strainer internal inspection; gauges replaced or calibrated; standpipe flow test and pressure-reducing valve full-flow test where applicable.
By ageSample sprinklers removed and lab-tested at 50 years (then every 10 years), fast-response sprinklers at 20 years, dry sprinklers at 10 years, and sprinklers in harsh environments every 5 years.

What changes for dry, preaction, and deluge systems

Dry and preaction systems add trip tests, air supply checks, and low-point drain maintenance before and during freezing weather. If your building has an unheated loading dock, attic, or parking deck, ask your contractor to show which tasks on your report apply to those zones.

Deficiencies and impairments

An inspection report should separate items that need correction from conditions that impair the system. When a system is impaired, NFPA 25 calls for an impairment procedure: notify the AHJ, insurer, and alarm company as required, and arrange a fire watch or other measures until it is restored.

Next step

Ask any contractor you are comparing to quote against the same scope: the NFPA 25 tasks due this year for your specific systems, plus any 5-year items that are coming due.

Find contractors near you

Sources

  1. NFPA 25, Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems (NFPA)
  2. New Jersey Division of Fire Safety (Uniform Fire Code, contractor certification)
  3. FDNY, New York City Fire Code
  4. Connecticut Office of State Fire Marshal (State Fire Safety Code)

NFPA standards are available to read free online from NFPA. Requirements depend on the edition your jurisdiction adopts; confirm with your authority having jurisdiction.